NEWS / NOV.2026
PJM aims to complete data center interconnection studies in one year
On November 16, US grid operator PJM announced that it planned to submit a proposal to the regulator that evening for a joint study of how to connect new power plants and supply large customers, including data centers. The proposed twelve-month period would run through finalization of the interconnection agreement.

PJM proposes cutting the process that precedes grid connection for power plants and large customers from 24 months to 12 months
On November 16, 2026, PJM announced that it planned to file a proposal with the Federal Energy Regulatory Commission (FERC) that evening to study, over twelve months, how to connect new power plants and serve large customers, including data centers. The US grid operator is requesting a 60-day comment period and a decision within 120 days of filing. FERC sets those deadlines.
For a power generator, the current benchmark is 24 months from application to interconnection agreement. PJM had already presented the timetable for its Fast Energization proposal on October 26. It allows four months for an initial review, seven months to study the impact on the grid and one month to finalize the agreement. Construction and energization fall outside that period. PJM expects that some large customers could receive power on an interim basis while grid upgrades are underway.
PJM believes new power plants and transmission lines are coming online too slowly to keep up with demand. By reviewing generation projects alongside the needs of large customers, the operator hopes to avoid repeating some analyses. Applicants would receive a preliminary assessment before providing the financial guarantees that PJM wants to require earlier in the process.
In October, the Data Center Coalition, which represents the data center industry, raised concerns with PJM’s board. It feared the joint review could complicate interconnections and lengthen wait times, Reuters reports.
On November 13, Defend Intelligence examined how data centers could affect the price of power capacity secured at auction. PJM’s proposal also addresses the cost of grid work. Its effect on total electricity bills for households and businesses remains unknown.
If a transmission line needed an upgrade to supply a data center, the study would specify the work required and estimate its cost. According to PJM, states and distribution utilities could use that estimate to determine what share of the cost to charge the applicant.